Which report must be used to inform the project board of a predicted deviation from agreed stage limits?

A.
End stage report
Answers
A.
End stage report
B.
Checkpoint report
Answers
B.
Checkpoint report
C.
Highlight report
Answers
C.
Highlight report
D.
Exception report
Answers
D.
Exception report
Suggested answer: D

Explanation:

The Exception Report must be used to inform the project board of a predicted deviation from the agreed stage limits. This report is triggered when stage tolerances are forecasted to be exceeded, requiring the project board's decision on how to proceed with the project.