Which control must be used as a minimum requirement for applying the 'progress' theme?

A.
A project plan
Answers
A.
A project plan
B.
Tolerances
Answers
B.
Tolerances
C.
An Issue register
Answers
C.
An Issue register
D.
Highlight reports
Answers
D.
Highlight reports
Suggested answer: B

Explanation:

Tolerances are a minimum requirement for applying the 'progress' theme in PRINCE2. They define the allowable deviations in time, cost, quality, scope, risk, and benefit objectives that do not require escalation to higher management levels. This control mechanism ensures that the project operates within agreed boundaries without frequent upper management intervention.

Reference: = PRINCE2 7 Foundation handbook and online resources