Question 328 - PRINCE2-7-Foundation discussion

Report
Export

Which management level should approve a course of action if project-level tolerance is exceeded?

A.
Corporate, programme management or the customer
Answers
A.
Corporate, programme management or the customer
B.
Project board
Answers
B.
Project board
C.
Project manager
Answers
C.
Project manager
D.
Team manager
Answers
D.
Team manager
Suggested answer: A

Explanation:

If project-level tolerance is exceeded, the course of action must be approved at a level higher than the project board, typically by corporate, programme management, or the customer. This ensures that higher management levels are involved in decisions when significant variances that might impact project viability or strategic alignment occur.

Reference: = PRINCE2 7 Foundation handbook and online resources