Which describes a time-driven control?

A.
The dates for the project's end stage assessment included in the project plan
Answers
A.
The dates for the project's end stage assessment included in the project plan
B.
The expected frequency of progress reports specified in a work package
Answers
B.
The expected frequency of progress reports specified in a work package
C.
The expected dates for planned checks of specialist products included in a stage plan
Answers
C.
The expected dates for planned checks of specialist products included in a stage plan
D.
The planned exception assessment meeting to authorize a requested exception plan
Answers
D.
The planned exception assessment meeting to authorize a requested exception plan
Suggested answer: B

Explanation:

A time-driven control is defined as a monitoring system that is based on a fixed time interval, such as weekly or monthly progress reports. The expected frequency of progress reports specified in a work package represents a time-driven control, where updates are required at predefined intervals irrespective of the state of the project at those times.

Reference: = PRINCE2 7 Foundation handbook and online resources