Which are purposes of the 'directing a project' process?

1. To enable the project board to be accountable for a project's success by making key decisions

2. To enable the project board to authorize work packages

3. To enable the project board to prepare the communication management approach

4. To enable the project board to exercise overall control of a project

A.
1 and 2
Answers
A.
1 and 2
B.
2 and 3
Answers
B.
2 and 3
C.
3 and 4
Answers
C.
3 and 4
D.
1 and 4
Answers
D.
1 and 4
Suggested answer: D

Explanation:

The purposes of the 'directing a project' process are to enable the project board to be accountable for the project's success by making key decisions (1) and to exercise overall control of the project (4). This process ensures that strategic guidance and oversight are maintained, but does not directly involve the project board in authorizing work packages or preparing communication approaches---that's handled by the project manager.

Reference: = PRINCE2 7 Foundation handbook and online resources