Identify the missing words in the following sentence.

The 'managing product delivery' process provides a controlled link between [ ? ] and a project manager.

A.
project assurance
Answers
A.
project assurance
B.
the project board
Answers
B.
the project board
C.
the corporate, programme management or the customer
Answers
C.
the corporate, programme management or the customer
D.
a team manager
Answers
D.
a team manager
Suggested answer: D

Explanation:

The 'managing product delivery' process provides a controlled link between a team manager and the project manager. This process ensures that the work assigned to the team is authorized and managed according to the project's requirements, facilitating clear communication and effective delivery of project products.

Reference: = PRINCE2 7 Foundation handbook and online resources