Which statement BEST describes how approved plans enable control?

A.
By defining the quality specifications of individual products in product descriptions
Answers
A.
By defining the quality specifications of individual products in product descriptions
B.
By enabling the controlled consideration of business opportunities
Answers
B.
By enabling the controlled consideration of business opportunities
C.
By defining the benefits that need to be realized through the benefits management approach
Answers
C.
By defining the benefits that need to be realized through the benefits management approach
D.
By defining what is within the approved project scope to avoid scope creep
Answers
D.
By defining what is within the approved project scope to avoid scope creep
Suggested answer: D

Explanation:

Approved plans enable control primarily by defining what is included within the approved project scope, which helps to avoid scope creep. These plans establish clear boundaries and deliverables for the project, which are essential for managing resources and ensuring that the project team remains focused on delivering the specified outputs without unnecessary expansion of the project scope.

Reference: (PRINCE2 7 Foundation Handbook, AXELOS)