Which process has the objective of confirming that acceptance criteria have been met?

A.
Controlling a stage
Answers
A.
Controlling a stage
B.
Directing a project
Answers
B.
Directing a project
C.
Managing product delivery
Answers
C.
Managing product delivery
D.
Closing a project
Answers
D.
Closing a project
Suggested answer: D

Explanation:

In PRINCE2, the 'Closing a Project' process has the objective of confirming that the project's products are acceptable and meet the established acceptance criteria. This process ensures that the project has delivered the required outputs as agreed upon, and these outputs are approved and accepted by the customer.

Reference: PRINCE2 Foundation Guide, 'Closing a Project' section