Question 359 - PRINCE2-7-Foundation discussion

Report
Export

The project board needs to confirm that there is enough information to initiate the project.

What should the project board review?

A.
Project brief
Answers
A.
Project brief
B.
Business case
Answers
B.
Business case
C.
Benefits management approach
Answers
C.
Benefits management approach
D.
Project plan
Answers
D.
Project plan
Suggested answer: A

Explanation:

The Project Board must review the Project Brief to confirm there is enough information to initiate the project. The Project Brief includes the outline Business Case, the project's objectives, and how the project fits into the organization's objectives. This document is essential for the Project Board to understand what the project is intended to achieve, ensuring alignment with organizational goals and confirming that the project remains viable before moving forward into the initiation stage.

Reference: PRINCE2 Foundation training manual and official handbook.