Which TWO are objectives of the closing a project: process?

1. To ensure the benefit reviews enable the project benefits to the confirmed

2. To update the business case so that the project hoard can decide whether to continue with the project

3. To ensure that the project team deliver the products to quality expectations

4. To hand over any open threats to operations

A.
1 and 2
Answers
A.
1 and 2
B.
2 and 3
Answers
B.
2 and 3
C.
3 and 4
Answers
C.
3 and 4
D.
1 and 4
Answers
D.
1 and 4
Suggested answer: D

Explanation:

The objectives of the 'Closing a Project' process in PRINCE2 include ensuring that provisions are made for ongoing benefit realization reviews (objective 1) and handing over any ongoing issues, including unresolved risks or threats, to operational maintenance or support teams (objective 4). This process is about wrapping up the project cleanly, ensuring that all project objectives related to closure are met, and preparing for the sustained realization of benefits post-project.

Reference: = PRINCE2 7 Foundation Training Manual and official PRINCE2 website documentation