The project manager needs to record what will make file Users satisfied with the final product

Where should the project manager record this?

A.
Quality register
Answers
A.
Quality register
B.
Project plan
Answers
B.
Project plan
C.
Project product description
Answers
C.
Project product description
D.
Quality management approach
Answers
D.
Quality management approach
Suggested answer: C

Explanation:

The Project Product Description in PRINCE2 is a document where the project manager records specific requirements that must be met for the user to accept the final product, including criteria for user satisfaction. This document provides a detailed description of the purpose, composition, derivation, and quality criteria of the project's main deliverable or product.

Reference: = PRINCE2 7 Foundation Training Manual and official PRINCE2 website documentation