Which details the identified threats and Opportunities related in the project?

A.
Risk management approach
Answers
A.
Risk management approach
B.
Project plan
Answers
B.
Project plan
C.
Risk register
Answers
C.
Risk register
D.
Business case
Answers
D.
Business case
Suggested answer: C

Explanation:

The Risk Register in PRINCE2 is a document used to detail all identified risks associated with the project, including both threats and opportunities. This register includes descriptions of each risk, their status, and the responses planned or taken to manage these risks, serving as a key tool for risk management throughout the project lifecycle.

Reference: = PRINCE2 7 Foundation Training Manual and official PRINCE2 website documentation