Which member of the project management team should secure funding for the project before the project stars?

A.
Project executive
Answers
A.
Project executive
B.
Project manager
Answers
B.
Project manager
C.
Senior user
Answers
C.
Senior user
D.
senior supplier
Answers
D.
senior supplier
Suggested answer: A

Explanation:

In PRINCE2, the Project Executive is responsible for the overall success of the project, which includes securing the necessary funding before the project begins. This role is part of the project board and has the authority to commit organizational resources and funds, ensuring that the project is financially viable from start to finish.

Reference: = PRINCE2 7 Foundation Training Manual and official PRINCE2 website documentation