Which should define how tools will be used to support the information needs of the project team?

A.
Digital and data management approach
Answers
A.
Digital and data management approach
B.
Quality management approach
Answers
B.
Quality management approach
C.
Issue management approach
Answers
C.
Issue management approach
D.
Commercial management approach
Answers
D.
Commercial management approach
Suggested answer: A

Explanation:

The 'Digital and Data Management Approach' in PRINCE2 should define how tools and technologies will be utilized to support the information needs of the project team. This approach outlines how digital resources, data handling, and communication tools are to be deployed to enhance the effectiveness of information sharing and project management practices.

Reference: = PRINCE2 7 Foundation Training Manual and official PRINCE2 website documentation