In which process are the key decisions to control the project made?

A.
Directing a project
Answers
A.
Directing a project
B.
Initiating a project
Answers
B.
Initiating a project
C.
Managing a stage boundary
Answers
C.
Managing a stage boundary
D.
Controlling a stage
Answers
D.
Controlling a stage
Suggested answer: A

Explanation:

In PRINCE2, the 'Directing a Project' process is where the key decisions to control the overall project are made. This process involves the Project Board and is crucial for providing overall direction and management oversight throughout the lifecycle of the project, including key decision points such as project initiation, stage boundaries, and project closure.

Reference: = PRINCE2 7 Foundation Training Manual and official PRINCE2 website documentation