Which TWO are objectives of the 'starting up a project' process?

1. To create a common view of How the required quality will be achieved

2.To give authority to initiate the project

3. To appoint the resources needed to do the work to initiate the project

4. To ensure that projects are initiated based or agreed acceptance criteria for the project product.

A.
1 and 2
Answers
A.
1 and 2
B.
2 and 3
Answers
B.
2 and 3
C.
3 and 4
Answers
C.
3 and 4
D.
1 and 4
Answers
D.
1 and 4
Suggested answer: B

Explanation:

The objectives of the 'Starting up a Project' process in PRINCE2 include giving authority to initiate the project (ensuring there is a solid foundation before significant expenditure is committed), and appointing the resources needed to undertake the initiation phase of the project. This process sets the project up for success by confirming its scope, defining how it will be managed, and allocating the necessary resources.

Reference: = PRINCE2 7 Foundation Training Manual and official PRINCE2 website documentation