List of questions
Related questions
Question 397 - PRINCE2-7-Foundation discussion
What is a description of a leadership activity within a project?
A.
Understanding and working with different departments outside of the project team
B.
Agreeing a work package with a tear manager to deliver products using specific tools
C.
Ensuring that a co-located project team uses the agreed communication methods
D.
Creating a stage plan and product descriptions for the products to be created in the next stage
Your answer: