What is a description of a leadership activity within a project?

A.
Understanding and working with different departments outside of the project team
Answers
A.
Understanding and working with different departments outside of the project team
B.
Agreeing a work package with a tear manager to deliver products using specific tools
Answers
B.
Agreeing a work package with a tear manager to deliver products using specific tools
C.
Ensuring that a co-located project team uses the agreed communication methods
Answers
C.
Ensuring that a co-located project team uses the agreed communication methods
D.
Creating a stage plan and product descriptions for the products to be created in the next stage
Answers
D.
Creating a stage plan and product descriptions for the products to be created in the next stage
Suggested answer: A

Explanation:

A key leadership activity within a project involves understanding and effectively working with different departments outside of the project team. This includes managing stakeholder expectations, ensuring alignment with broader organizational goals, and facilitating cross-functional collaboration, which are essential for the successful delivery of project outcomes.

Reference: = PRINCE2 7 Foundation Training Manual and official PRINCE2 website documentation