Question 398 - PRINCE2-7-Foundation discussion
The project manager needs to define key information so that the project board can decide whether to proceed with planning the project in more detail.
In which process should the project manager define this information?
A.
Starting up a project
B.
Initiating a project
C.
Directing a project
D.
Managing a stage boundary