Question 399 - PRINCE2-7-Foundation discussion
The project manager reviews the project product description to identify the detailed requirement for each product.
In which step of the quality management technique should the project manager do this review?
A.
Gathering user inputs
B.
Accepting products ay
C.
Describing the quality management approach
D.
Controlling quality