List of questions
Related questions
Question 400 - PRINCE2-7-Foundation discussion
Which feature of a stage plan suggests that a project is in danger of scope creep?
A.
Stage plans are prepared by the project manager as the stage comes to an end
B.
Products identified in a stage plan cannot be traced back to the project plan
C.
The team delivering the stage plan includes staff from different parts of an organization
D.
it is not possible to implement remedial actions for an exception by updating a stage plan
Your answer:
0 comments
Sorted by
Leave a comment first