In which step of the risk management' technique should the organization's environment be considered?

A.
Identity
Answers
A.
Identity
B.
Assess
Answers
B.
Assess
C.
Plan
Answers
C.
Plan
D.
Implement
Answers
D.
Implement
Suggested answer: A

Explanation:

In the 'risk management' technique within PRINCE2, considering the organization's environment is essential during the 'Identify' step. This phase involves understanding the context in which the project operates, including external and internal factors that could affect the project. This context is crucial for identifying potential risks that could impact the project's objectives.

Reference: PRINCE2 7 Foundation resources on risk management technique.