ExamGecko
Question list
Search
Search

Question 411 - PRINCE2-7-Foundation discussion

Report
Export

Which plan is used to organize and control the work when executing a work package?

A.
team plan
Answers
A.
team plan
B.
A stage plan
Answers
B.
A stage plan
C.
A project plan,
Answers
C.
A project plan,
D.
An exception plan
Answers
D.
An exception plan
Suggested answer: A

Explanation:

When executing a Work Package, the Team Plan is used to organize and control the work. The Team Plan is derived from the Stage Plan and provides detailed allocations and explanations of how the team will deliver the work package assigned to them. It focuses specifically on the tasks and resources at the team level, detailing the schedule and resources needed to complete the work.

Reference: (PRINCE2 7 Foundation Handbook, AXELOS)

asked 23/09/2024
Sascha Mintenbeck
31 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first