Question 413 - PRINCE2-7-Foundation discussion
As part of the 'closing a project' process, the project manager needs to assess whether the outcomes are likely to deliver the expected performance improvements post-project.
In which step of 'business case management' technique should the project manager assess this?
A.
Develop
B.
Check ay
C.
Maintain
D.
Confirm
Your answer: