Question 413 - PRINCE2-7-Foundation discussion

Report
Export

As part of the 'closing a project' process, the project manager needs to assess whether the outcomes are likely to deliver the expected performance improvements post-project.

In which step of 'business case management' technique should the project manager assess this?

A.
Develop
Answers
A.
Develop
B.
Check ay
Answers
B.
Check ay
C.
Maintain
Answers
C.
Maintain
D.
Confirm
Answers
D.
Confirm
Suggested answer: C

Explanation:

During the 'Maintain' step of the 'business case management' technique in PRINCE2, the project manager assesses the ongoing viability of the project against the business case, including whether the outcomes are likely to deliver the expected performance improvements post-project. This is a continuous process that ensures the project remains aligned with business needs and expected benefits throughout its lifecycle.

Reference: PRINCE2 7 Foundation documentation on business case management.