Which describes a management activity within a project?

A.
Encouraging a project team to continue working on a particularly challenging product
Answers
A.
Encouraging a project team to continue working on a particularly challenging product
B.
Discussing project objectives with key stakeholders during a requirements gathering workshop
Answers
B.
Discussing project objectives with key stakeholders during a requirements gathering workshop
C.
Agreeing a work package with a team manager to deliver products within agreed tolerances
Answers
C.
Agreeing a work package with a team manager to deliver products within agreed tolerances
D.
Seeking feedback from team members to ensure they are still aligned to the project's objectives
Answers
D.
Seeking feedback from team members to ensure they are still aligned to the project's objectives
Suggested answer: C

Explanation:

In PRINCE2, a management activity within a project typically involves formal agreements and organizational actions. Agreeing on a work package with a team manager is a core management activity, where specific tasks, responsibilities, and tolerances are defined and communicated, ensuring that the project's delivery aligns with the planned objectives and constraints.

Reference: PRINCE2 7 Foundation study materials on project management activities.