Question 414 - PRINCE2-7-Foundation discussion
Which describes a management activity within a project?
A.
Encouraging a project team to continue working on a particularly challenging product
B.
Discussing project objectives with key stakeholders during a requirements gathering workshop
C.
Agreeing a work package with a team manager to deliver products within agreed tolerances
D.
Seeking feedback from team members to ensure they are still aligned to the project's objectives