Which TWO are objectives of the 'closing a project' process?

1. To confirm to the project board that each stage's products are approved

2. To review whether the project was delivered within time and cost tolerances

3. To confirm whether operational staff are happy to take ownership of the products

4. To confirm that there is authority to close the project

A.
1 and 2
Answers
A.
1 and 2
B.
2 and 3
Answers
B.
2 and 3
C.
3 and 4
Answers
C.
3 and 4
D.
1 and 4
Answers
D.
1 and 4
Suggested answer: B

Explanation:

The objectives of the 'closing a project' process in PRINCE2 include reviewing whether the project was delivered within time and cost tolerances (2) and confirming whether operational staff are happy to take ownership of the products (3). These objectives ensure the project has met its management expectations and that the product transition to operations is smooth and accepted by relevant stakeholders.

Reference: PRINCE2 7 Foundation guide on the 'closing a project' process.