According to the guidance for effective quality management, when should the requirements for a product be captured?

A.
When the project team realizes that the product is needed
Answers
A.
When the project team realizes that the product is needed
B.
When the project team needs to test the product
Answers
B.
When the project team needs to test the product
C.
When the project team needs to know whether the product has been approved
Answers
C.
When the project team needs to know whether the product has been approved
D.
When the project team needs to know how the product will be delivered
Answers
D.
When the project team needs to know how the product will be delivered
Suggested answer: A

Explanation:

In PRINCE2, the requirements for a product should be captured early in the process, specifically when the project team realizes the need for that product. This approach ensures that the project delivers what is actually required and expected. Capturing requirements early helps in detailed planning and allows for effective quality management throughout the product's development and delivery phases.

Reference: (PRINCE2 7 Foundation Handbook, AXELOS)