Identify the missing word in the following sentence:

[ ?] is a prediction made by studying historical data and past patterns.

A.
A forecast
Answers
A.
A forecast
B.
A project baseline
Answers
B.
A project baseline
C.
An exception
Answers
C.
An exception
D.
A highlight report
Answers
D.
A highlight report
Suggested answer: A

Explanation:

A forecast is a prediction made by studying historical data and past patterns. In project management, forecasting involves using data from the project's progress and external benchmarks to predict future project performance, helping in planning and decision-making processes.

Reference: (PRINCE2 7 Foundation Handbook, AXELOS)