Question 419 - PRINCE2-7-Foundation discussion

Report
Export

The project manager needs to monitor the progress of the stage.

Which combination of management products should the project manager review?

A.
Checkpoint reports AND work package descriptions
Answers
A.
Checkpoint reports AND work package descriptions
B.
Project plan AND project log
Answers
B.
Project plan AND project log
C.
Project plan AND work package descriptions
Answers
C.
Project plan AND work package descriptions
D.
Highlight report AND checkpoint report
Answers
D.
Highlight report AND checkpoint report
Suggested answer: D

Explanation:

To monitor the progress of a stage effectively, the project manager should review both the Highlight Report and Checkpoint Report. The Highlight Report provides a summary of the stage status to the Project Board, detailing overall progress and identifying any major issues. The Checkpoint Report, on the other hand, offers detailed updates from team managers or team members on the progress of their respective Work Packages. Together, these management products give a comprehensive view of stage progress.

Reference: (PRINCE2 7 Foundation Handbook, AXELOS)