Question 420 - PRINCE2-7-Foundation discussion

Report
Export

The project manager needs to monitor the progress of the stage.

Which combination of management products should the project manager review?

A.
Checkpoint reports AND work package descriptions
Answers
A.
Checkpoint reports AND work package descriptions
B.
Project plan AND project log
Answers
B.
Project plan AND project log
C.
Project plan AND work package descriptions
Answers
C.
Project plan AND work package descriptions
D.
Highlight report AND checkpoint report
Answers
D.
Highlight report AND checkpoint report
Suggested answer: D

Explanation:

Similar to question 411, the answer remains consistent for monitoring the progress of a stage. The combination of Highlight Reports and Checkpoint Reports provides the project manager with both high-level and detailed insights into the stage's progress. Highlight Reports summarize stage status for the Project Board, while Checkpoint Reports offer detailed progress updates from the team level.

Reference: (PRINCE2 7 Foundation Handbook, AXELOS)