Question 420 - PRINCE2-7-Foundation discussion
The project manager needs to monitor the progress of the stage.
Which combination of management products should the project manager review?
A.
Checkpoint reports AND work package descriptions
B.
Project plan AND project log
C.
Project plan AND work package descriptions
D.
Highlight report AND checkpoint report