Question 421 - PRINCE2-7-Foundation discussion
According to the 'manage by exception' principle, which statement about tolerances is CORRECT?
A.
Whenever authority is delegated to the project manager, the project board should set tolerances for the stage
B.
Whenever there is a forecast to exceed a tolerance, it should be escalated to the project board
C.
Whenever there is a forecast to exceed a tolerance, it should be resolved at the next monthly project board meeting
D.
Whenever authority is delegated to the team manager, the focus should be on delivering within time and cost tolerances