What should set the expected success level for benefits, time, cost, quality, scope, sustainability and risk?

A.
Performance target
Answers
A.
Performance target
B.
Project baseline
Answers
B.
Project baseline
C.
Integrated elements
Answers
C.
Integrated elements
D.
Project context
Answers
D.
Project context
Suggested answer: B

Explanation:

The expected success level for benefits, time, cost, quality, scope, sustainability, and risk in a project should be set by the project baseline. The baseline establishes the initial scope of what the project is expected to deliver, including standards and targets against which project performance can be measured.

Reference: PRINCE2 7 Foundation sources on project planning and control.