Which term is defined as being achieved as a result of the activities undertaken to facilitate the change?

A.
Outcome
Answers
A.
Outcome
B.
Benefit
Answers
B.
Benefit
C.
output
Answers
C.
output
D.
Request for change
Answers
D.
Request for change
Suggested answer: A

Explanation:

In PRINCE2, an 'outcome' is defined as the result achieved by the project after implementing changes through its activities. Outcomes are the new states enabled by the project's outputs, differing from benefits in that they are not necessarily quantified as improvements until later evaluated as such.

Reference: PRINCE2 7 Foundation documentation on project outputs, outcomes, and benefits.