Which role is responsible for focusing on the safety and well-being of the project team?

A.
Project executive
Answers
A.
Project executive
B.
Project board
Answers
B.
Project board
C.
Project manager
Answers
C.
Project manager
D.
Team manager
Answers
D.
Team manager
Suggested answer: D

Explanation:

In the PRINCE2 framework, the team manager is the role primarily responsible for the welfare, including the safety and well-being, of the project team. This role involves managing the team environment and ensuring that team members are supported throughout the project's lifecycle.

Reference: PRINCE2 7 Foundation guide and resources detailing project roles and responsibilities.