Question 425 - PRINCE2-7-Foundation discussion

Report
Export

When should the project baseline be updated in order ta meet the purpose of the 'issues' practice?

A.
When a request for change is recorded on the issue register
Answers
A.
When a request for change is recorded on the issue register
B.
When a business opportunity has been recognized
Answers
B.
When a business opportunity has been recognized
C.
When the project manager receives a request for change
Answers
C.
When the project manager receives a request for change
D.
When a change has been approved by the change authority
Answers
D.
When a change has been approved by the change authority
Suggested answer: D

Explanation:

In PRINCE2, the project baseline should be updated when a change has been formally approved by the change authority. This is because the baseline represents the agreed standards and plan against which the project's performance is measured. Updating the baseline after the approval of changes ensures that the project documentation accurately reflects the current scope, timescales, and resource allocations, which are essential for tracking progress and managing by exception effectively.

Reference: (PRINCE2 7 Foundation Handbook, AXELOS)