List of questions
Related questions
Question 428 - PRINCE2-7-Foundation discussion
According to the 'exception management technique, which roles are MOST LIKELY to identity issues that exceed stage tolerances?
A.
Project executive AND senior user
B.
Senior supplier AND team manager
C.
Project executive AND project manager
D.
Project manager AND team manager
Your answer:
0 comments
Sorted by
Leave a comment first