Identify the missing word(s) in the following sentence:

[ ? ] dependency is one between two products of a project, over which the project team has control.

A.
An internal
Answers
A.
An internal
B.
A schedule-driven
Answers
B.
A schedule-driven
C.
An external
Answers
C.
An external
D.
A resource-driven
Answers
D.
A resource-driven
Suggested answer: A

Explanation:

In PRINCE2, an 'internal' dependency refers to a relationship between two products of a project that is under the control of the project team. These dependencies are managed within the project's boundaries, unlike external dependencies which involve elements outside the project's direct control.

Reference: PRINCE2 7 Foundation materials on product dependencies.