Question 429 - PRINCE2-7-Foundation discussion
Identify the missing word(s) in the following sentence:
[ ? ] dependency is one between two products of a project, over which the project team has control.
A.
An internal
B.
A schedule-driven
C.
An external
D.
A resource-driven