Which action should the project manager take when reviewing progress to assess the 'health' of a stage?

A.
Capture lessons that may assist in the monitoring and control of this project
Answers
A.
Capture lessons that may assist in the monitoring and control of this project
B.
Review the quality of the relationships in the organizational
Answers
B.
Review the quality of the relationships in the organizational
C.
Increase the frequency of event-driven controls to monitor stage progress
Answers
C.
Increase the frequency of event-driven controls to monitor stage progress
D.
Identify whether issues are resolved in a timely manner or left unmanaged
Answers
D.
Identify whether issues are resolved in a timely manner or left unmanaged
Suggested answer: D

Explanation:

When reviewing the progress to assess the 'health' of a stage, the project manager should focus on how issues are being managed. Identifying whether issues are resolved timely or remain unmanaged is crucial for maintaining the health of the project stage and ensuring that risks do not escalate and affect the project's success.

Reference: PRINCE2 7 Foundation handbook on stage management and issue resolution.