When is a work breakdown structure MOST useful?

A.
When there are multiple work packages with a mix of internal and external resources
Answers
A.
When there are multiple work packages with a mix of internal and external resources
B.
in a simple project with one work package for the work of a small team
Answers
B.
in a simple project with one work package for the work of a small team
C.
When establishing a change authority aligned to project tolerances
Answers
C.
When establishing a change authority aligned to project tolerances
D.
When assuring business, user and supplier aspects of project performance
Answers
D.
When assuring business, user and supplier aspects of project performance
Suggested answer: A

Explanation:

A Work Breakdown Structure (WBS) is most useful when managing projects with multiple work packages that involve a combination of internal and external resources. The WBS helps in organizing and defining the total scope of the project by breaking down the project deliverables into smaller, more manageable components, facilitating better planning, allocation, and control of resources.

Reference: (PRINCE2 7 Foundation Handbook, AXELOS)