Which TWO are objectives of the 'starting up a project' process?

1. To provide an interface between the corporate layer and the project

2. To provide the required authority to initiate the project

3. To plan the work required for project initiation

4. To provide business justification for initiating the project

A.
1 and 2
Answers
A.
1 and 2
B.
2 and 3
Answers
B.
2 and 3
C.
3 and 4
Answers
C.
3 and 4
D.
1 and 4
Answers
D.
1 and 4
Suggested answer: D

Explanation:

The objectives of the 'Starting Up a Project' process include providing an interface between the corporate or program environment and the project (objective 1) and providing business justification for initiating the project (objective 4). This process ensures that the project is viable and worthwhile before further resources are committed and that there is a clear link to corporate strategies and ongoing work.

Reference: (PRINCE2 7 Foundation Handbook, AXELOS)