When does the 'directing a project' process start?

A.
When the project manager submits the project brief for approval
Answers
A.
When the project manager submits the project brief for approval
B.
When the request to authorize a project is received
Answers
B.
When the request to authorize a project is received
C.
After the project has been authorized by the business layer
Answers
C.
After the project has been authorized by the business layer
D.
After the project mandate has been received
Answers
D.
After the project mandate has been received
Suggested answer: B

Explanation:

The 'Directing a Project' process in PRINCE2 starts when the request to authorize a project is received. This request usually comes after the initial project setup has been reviewed and there is a need to formally authorize the project to begin detailed planning and execution. This is a crucial step in establishing the governance framework that will guide the project's overall direction.

Reference: (PRINCE2 7 Foundation Handbook, AXELOS)