Question 433 - PRINCE2-7-Foundation discussion

Report
Export

The project manager needs to plan the reviews to confirm whether the expected measurable improvements have been achieved.

Which management product should the project manager produce?

A.
Benefits management approach
Answers
A.
Benefits management approach
B.
Business case
Answers
B.
Business case
C.
Quality management approach
Answers
C.
Quality management approach
D.
End project report
Answers
D.
End project report
Suggested answer: A

Explanation:

The 'benefits management approach' is the management product the project manager should produce to plan reviews for confirming whether the expected measurable improvements have been achieved. This approach outlines how and when the benefits of the project are to be measured and assessed, aligning the project's deliverables with the intended outcomes.

Reference: PRINCE2 7 Foundation documentation on benefits management.