Which TWO are objectives of the 'managing a stage boundary' process?
1. To confirm to the project board that there are no products outstanding for the stage
2. To ensure that expectations are managed via accurate reporting to the project manager during a stage
3. To ensure that the project management team is not distracted by delivering additional products during the stage
4. To request the project board to approve work to start on the next stage
A.
1 and 2
B.
2 and 3
C.
3 and 4
D.
1 and 4