ExamGecko
Question list
Search
Search

Question 432 - PRINCE2-7-Foundation discussion

Report
Export

Which TWO are objectives of the 'managing a stage boundary' process?

1. To confirm to the project board that there are no products outstanding for the stage

2. To ensure that expectations are managed via accurate reporting to the project manager during a stage

3. To ensure that the project management team is not distracted by delivering additional products during the stage

4. To request the project board to approve work to start on the next stage

A.
1 and 2
Answers
A.
1 and 2
B.
2 and 3
Answers
B.
2 and 3
C.
3 and 4
Answers
C.
3 and 4
D.
1 and 4
Answers
D.
1 and 4
Suggested answer: D

Explanation:

The objectives of the 'managing a stage boundary' process include confirming to the project board that there are no products outstanding for the stage (1) and requesting the project board to approve work to start on the next stage (4). These objectives ensure that each stage is properly concluded before moving to the next, maintaining project governance and alignment with planned objectives.

Reference: PRINCE2 7 Foundation materials on the 'managing a stage boundary' process.

asked 23/09/2024
Amirouche Rahani
48 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first