Question 439 - PRINCE2-7-Foundation discussion
The project manager has proposed that a request for change be implemented, but the change authority has asked for more information.
In which step of the 'issue management technique should the change authority request this information?
A.
Deciding on changes
B.
Implementing changes
C.
Assessing issues
D.
Capturing issues