The project manager has proposed that a request for change be implemented, but the change authority has asked for more information.

In which step of the 'issue management technique should the change authority request this information?

A.
Deciding on changes
Answers
A.
Deciding on changes
B.
Implementing changes
Answers
B.
Implementing changes
C.
Assessing issues
Answers
C.
Assessing issues
D.
Capturing issues
Answers
D.
Capturing issues
Suggested answer: C

Explanation:

When the change authority asks for more information regarding a proposed change, this occurs during the 'Assessing issues' step of the 'issue management technique' in PRINCE2. This step involves evaluating the impact and implications of issues or changes, including requesting additional information necessary to make informed decisions.

Reference: PRINCE2 7 Foundation resources on issue and change management.