Which is a description of a purpose of the 'managing product delivery' process?

A.
To agree requirements for the delivery of specific products between the project manager and the team manager
Answers
A.
To agree requirements for the delivery of specific products between the project manager and the team manager
B.
To report progress towards the delivery of a stage's products to the project board
Answers
B.
To report progress towards the delivery of a stage's products to the project board
C.
To recognize that the project has no further contribution make towards achieving project objectives
Answers
C.
To recognize that the project has no further contribution make towards achieving project objectives
D.
To plan how the project will approach the work to deliver the project products
Answers
D.
To plan how the project will approach the work to deliver the project products
Suggested answer: A

Explanation:

The purpose of the 'managing product delivery' process in PRINCE2 is to control the link between the project manager and the team managers. This process ensures that the work on products meets the requirements specified by the project and is agreed upon between the project manager and the team manager, focusing on the acceptance, execution, and delivery of work packages.

Reference: PRINCE2 7 Foundation materials on the 'managing product delivery' process.