Question 449 - PRINCE2-7-Foundation discussion
Which statement about the 'manage by stages' principle is CORRECT?
A.
The project board should authorize multiple stages at the same time
B.
The end of a stage should provide a control point for the project board
C.
A project should have fewer, longer stages when the risk exposure is high
D.
A project should have separate stages to plan, deliver and close the project