Which statement about the 'manage by stages' principle is CORRECT?

A.
The project board should authorize multiple stages at the same time
Answers
A.
The project board should authorize multiple stages at the same time
B.
The end of a stage should provide a control point for the project board
Answers
B.
The end of a stage should provide a control point for the project board
C.
A project should have fewer, longer stages when the risk exposure is high
Answers
C.
A project should have fewer, longer stages when the risk exposure is high
D.
A project should have separate stages to plan, deliver and close the project
Answers
D.
A project should have separate stages to plan, deliver and close the project
Suggested answer: B

Explanation:

The 'manage by stages' principle in PRINCE2 dictates that the end of each stage provides a control point at which the project board can review progress, reassess project viability, and decide on the next steps. This approach allows for regular monitoring and decision-making, ensuring that the project remains aligned with its objectives and within its tolerances.

Reference: PRINCE2 7 Foundation guide on the 'manage by stages' principle.