Which common project context relates to the need to engage with external suppliers to deliver part of the project?

A.
Commercial
Answers
A.
Commercial
B.
Delivery method
Answers
B.
Delivery method
C.
Organizational
Answers
C.
Organizational
D.
Scale
Answers
D.
Scale
Suggested answer: A

Explanation:

The need to engage with external suppliers for delivering parts of the project is commonly related to the 'Commercial' project context in PRINCE2. This context involves considerations around contractual arrangements, procurement, and the management of supplier relationships which are crucial for projects relying on external vendors for key components or services.

Reference: (PRINCE2 7 Foundation Handbook, AXELOS)