What is the BEST reason to perform the risk practice?

A.
To ensure risks are assigned to people who will own and action them satisfactorily
Answers
A.
To ensure risks are assigned to people who will own and action them satisfactorily
B.
To establish a supportive risk culture to enable decision-making
Answers
B.
To establish a supportive risk culture to enable decision-making
C.
To ensure stop-go decisions at stage boundaries are risk-informed
Answers
C.
To ensure stop-go decisions at stage boundaries are risk-informed
D.
To identiDfy and manage risks to project objectives
Answers
D.
To identiDfy and manage risks to project objectives
Suggested answer: D

Explanation:

The primary reason to perform the risk practice within a PRINCE2 project is to identify and manage risks that could affect the project's objectives. Effective risk management ensures that potential threats and opportunities are adequately assessed and handled to minimize negative impacts and leverage positives, thereby safeguarding the project's success.

Reference: PRINCE2 7 Foundation materials on risk management practices.