What is the BEST reason to perform the risk practice?
A.
To ensure risks are assigned to people who will own and action them satisfactorily
B.
To establish a supportive risk culture to enable decision-making
C.
To ensure stop-go decisions at stage boundaries are risk-informed
D.
To identiDfy and manage risks to project objectives