Question 458 - PRINCE2-7-Foundation discussion
How should the 'progress' practice be used?
A.
To define how the products will be delivered to enable control
B.
To predict whether the benefits will exceed the costs
C.
To identify opportunities that may make the project more successful
D.
To deliver change which will benefit people in their day-to-day work