Who determines when it is appropriate to update the Sprint Backlog during a Sprint?

A.
The Project Manager.
Answers
A.
The Project Manager.
B.
The Development Team.
Answers
B.
The Development Team.
C.
The Scrum Team.
Answers
C.
The Scrum Team.
D.
The Product Owner.
Answers
D.
The Product Owner.
Suggested answer: B