Five new Scrum Teams have been created to build one product. A few of the developers on one of the Development Teams ask the Scrum Master how to coordinate their work with the order teams. What should the Scrum Master do?

A.
Teach the Product Owner to work with the lead developers on ordering Product Backlog in a way to avoid too much technical and development overlap during a Sprint.
Answers
A.
Teach the Product Owner to work with the lead developers on ordering Product Backlog in a way to avoid too much technical and development overlap during a Sprint.
B.
Teach them that it is their responsibility to work with the other teams to create an integrated increment.
Answers
B.
Teach them that it is their responsibility to work with the other teams to create an integrated increment.
C.
Collect the Sprint tasks from the teams at the end of their Sprint Planning and merge that into a consolidated plan for the entire Sprint.
Answers
C.
Collect the Sprint tasks from the teams at the end of their Sprint Planning and merge that into a consolidated plan for the entire Sprint.
D.
Visit the five teams each day to inspect that their Sprint Backlogs are aligned.
Answers
D.
Visit the five teams each day to inspect that their Sprint Backlogs are aligned.
Suggested answer: C